KPI dashboard
CONFIDENTIAL · DEMO DATA
Cx Custodia
Portfolio Turnover Report
CONFIDENTIAL
Executive & investor briefing

Portfolio Turnover & Commissioning

Reporting period Q3 2026·As of July 18, 2026·2 active projects · 160 systems
Turnover
74%
118 / 160 systems transferred
ITRs complete
2,610
of 3,520 · 74% · 910 open
Punch list
142
open · 1,180 closed · 89% rate
Energized (NOE)
19 / 48
systems live across portfolio
Time to turnover
74 d
avg, RFCC → turnover
Executive summary

Portfolio turnover reached 74%, up 6 points in the quarter, led by Helios Unit 2 nearing completion at 87%. Commissioning throughput is tracking ahead of the ITR scope curve, and the punch-list close rate held at 89%. Energization remains the gating milestone: 19 of 48 systems are live, with two NOE approvals pending at Helios. Vesta is earlier in its cycle at 61% and is the focus for the coming quarter.

Commissioning burn-up
▬ Completed╌ Scope
W1W4W8
Turnover by project
HELIOS87% · target Sep 30
VESTA61% · target Nov 15
Portfolio74%
Project detail
ProjectTurnoverSystemsITRsPunch openEnergizedTarget
HELIOS · Helios Thermal Storage — Unit 2 (demo)87%47 / 541,204 / 1,4123812 / 18Sep 30
VESTA · Vesta Energy Park (demo)61%39 / 64892 / 1,460714 / 22Nov 15
Portfolio total74%118 / 1602,610 / 3,52014219 / 48Q4 2026
On track

Helios Unit 2 on schedule for full turnover by end of Q3; RFCC transfers 94% complete.

Watch

Two NOE approvals pending at Helios (SG-02, T-102); DCS commissioning is the critical path.

Next quarter

Ramp Vesta commissioning; clear 71 open punch items ahead of first custody transfers.

© 2026 Antora Energy · Confidential — do not distributeGenerated Jul 18, 2026 · v1.0 · demo data